1 Mount Pleasant Cottages

£103,200.00

The renovation/construction period starts on September 1, 2024, and is scheduled to be completed within three months. If the final payment is not made within three months of the completion date, 10% monthly interest will be applied to any outstanding amount.

Category:
No. Description Amount (£) VAT (20%) (£) Total (£)
3.1 Repairs and Removals 7,500 1,500 9,000
3.2 Complete Electrical Rewiring 8,000 1,600 9,600
3.3 Full Plumbing Replacement and Installation 7,000 1,400 8,400
3.4 Skimming & Other Installation 6,000 1,200 7,200
3.5 Interior Ceiling Repairs and Replacement 3,500 700 4,200
3.6 Bathroom x 2 Refurbishment 12,000 2,400 14,400
3.7 Kitchen Renovation 9,000 1,800 10,800
3.8 Complete Painting and Decorating 10,000 2,000 12,000
3.9 Floor & Carpet Replacement 8,000 1,600 9,600
3.10 Window and Door Replacement 7,000 1,400 8,400
3.11 Exterior Work and Roof Repairs 8,000 1,600 9,600
Total Contract Amount 86,000 17,200 103,200